How to update the Due Date for a Human task programatically
Hi
I am trying to implement a Process which has multiple Vendor Activity Tasks.
The Key element here is to implement a SLA metrics for each task.
I need to calculate whether each task was completed in Due time.
I am planning to use the Property available in the Bonita studio for setting the Due date for each task/activity.
This works great .
But my problem is that I need to consider Weekends as out side SLA. The tool should calculate for Days from Monday to Friday. Saturday and Sunday are excluded.
In the Bonita Studio, Under General ->Portal -> Estimated Duration , I can only set a fixed number of Days.
I dont see the Option of Writing a script there.
Hence I need to find a way to implement a method to update the Due date for a Task programatically.
The Example mention in the Below link is great.
http://community.bonitasoft.com/questions-and-answers/set-due-date-progr...
But my problem is that I dont know how to implement the same in Bonita 7.3.3
I could add the code to a operation section for a task but what should be on the Left hand side of the Section.
Kindly suggest with Steps as to how we could implement a code to change the Due Date for Human Tasks
Thanks
Dibyajit
Comments
Hi Lionel
Thanks for the Response.
What version of Bonita Studio are you using.
For me , I am using 7.3.3 and there is no pencil icon there.
Its just a standard section called Estimated duration and I can only select numbers. No option for Script.
regards
Dibyajit
Hi
I just checked out Bonita 7.4.2 community edition.
The script option is available there.
Not in 7.3.3.