Hello,

I have seen that one is able to start processes on a given schedule, but is it possible to make it so that a process can only end hourly, for example? So, if I have a simple process involving only 1 human task, when that task is completed, the process will only proceed to the end if it is the start of a new hour (exactly _:00). If the human task was completed at 5:50, I would like Bonita to wait until 6:00 to allow the process to end. If you can’t do this with an entire process, can you do something like it for a task?

Thanks

I have created the functionality I wanted by using a Timer with a script that gets the amount time until the next hour and returns that value as the delay duration for the timer. It seems to behave exactly how I want.

Hello
Could you share the code how you achieved it.

 