What are the startDate and lastUpdate values on process_instance table?

Hi

We have noticed that for many of our cases in progress, having some completed tasks, the lastUpdate value is the same as the startDate value in the process_instance table.

We have developed our own application, which displays the start date and the last updated date to our users. We are reading data from the process_instance table and assumed that every time a task is submitted the lastUpdate field on this table will be updated accordingly.

Could you please clarify what is the lastUpdate value and the startDate value in the process_instance table?

Regards

Hi,

startDate is the date / time stamp at which the process was instantiated.

lastUpdateDate is the date / time stamp when the line in the database table process_instance was last modified.

Usually, a process instance passes through the 3 following states: INITIALIZING (id=0), which is a very temporary state. It then reaches the state STARTED (id=1), and stays in that state until the process finished =, with state COMPLETED (id=6) or FAILED (id=7) in case an ON_FINISH connector fails. When the state changes, the lastUpdateDate is updated.

When a task is executed (whether it succeeds of fails), it does not alter the line in the database table process_instance, so lastUpdateDate is not updated.

Indeed, that being said, the lastUpdateDate field is not very useful.